Hi i'm Prasanth,
I would like to know default workflow of task updates and timesheets of
Projectserver 2007 from perspective of project manager and team member.
When a Project manager assigns a
task to team member he is not able to see the tasks under mytasks but can see
them under mytimesheet.Many small organisations have only one manager who
approves both timesheets and task updates of team members.How can i achieve
this in project server 2007 as in project server 2003.