Default workflow of tomesheets and task updates

P

Prasanth

Hi i'm Prasanth,

I would like to know default workflow of task updates and timesheets of
Projectserver 2007 from perspective of project manager and team member.
When a Project manager assigns a
task to team member he is not able to see the tasks under mytasks but can see
them under mytimesheet.Many small organisations have only one manager who
approves both timesheets and task updates of team members.How can i achieve
this in project server 2007 as in project server 2003.
 
G

Gérard Ducouret

Hello Prasanth,

The administrator of your Project Server has to set a Default Assignment
Owner for each resource (Edit resource in the Resource Center)

Hope this helps,

Gérard Ducouret
 