J
John
When a task is split, what level of control do you have over the
remaining split portion of the task? e.g. Task starts Monday 9am for 3
days duration, split after 2 days and want the remaining 1d to begin
say from 14:00 on the Friday.
When using the split task it always constrains to the start of the day
- I've found that by changing the Gantt Timescale to a more granular
timecale such as hours allows a little more precision, but this seems
a gludge - any thoughts gang?
remaining split portion of the task? e.g. Task starts Monday 9am for 3
days duration, split after 2 days and want the remaining 1d to begin
say from 14:00 on the Friday.
When using the split task it always constrains to the start of the day
- I've found that by changing the Gantt Timescale to a more granular
timecale such as hours allows a little more precision, but this seems
a gludge - any thoughts gang?