Delegate to multiple resources?

E

elenoir

I have a couple of questions:
1. Is it possible to delegate to multiple resources in PWA?
2. I am having issues with my projects not showing up correctly in Project
Center, it seems to have older versions. I've tried to republish a few times,
but this doen't help. Individuals can see the most recent tasks in their
"Tasks" menu, but not in the Project Center. If I open projects from the
Project Center using Project pro, it brings me to a correct updated project
plan, but if I try to look at it in PWA, it's an old version. Does anyone
know who to solve this?
Any help is greatly apprecited.
Thanks a lot!
Elvira
 
D

Dale Howard [MVP]

Elvira --

1. No. Task delegation is "one to one" only.

2. Open the projects in question and then click Collaborate - Publish -
Project Plan. This will "synch up" the data between the Project Center and
the actual Microsoft Project plan.

Hope this helps.
 
E

elenoir

Dale,
2. I've tried this too and it doesn't help, the most bizarre thing is that
in the first view of the Project Center (where all currently available on the
server projects are listed) I see the right data (start and finish dates,
etc.), but when I pick a particula project, it brings me to the same old
version. Is there anything else I can try? Would my only alternative be
deleting the project off the server?
Thanks!
Elvira
 
D

Dale Howard [MVP]

Elvira --

Are you seeing errors in the server's application event log? It sounds like
the act of publishing is not completing properly. Let us know what you
find.
 
E

elenoir

Dale,
There was some kind of error, I've tried to republish gain and it synched
up. As always, Thanks a lot for your help!
Elvira
 