E
elenoir
I have a couple of questions:
1. Is it possible to delegate to multiple resources in PWA?
2. I am having issues with my projects not showing up correctly in Project
Center, it seems to have older versions. I've tried to republish a few times,
but this doen't help. Individuals can see the most recent tasks in their
"Tasks" menu, but not in the Project Center. If I open projects from the
Project Center using Project pro, it brings me to a correct updated project
plan, but if I try to look at it in PWA, it's an old version. Does anyone
know who to solve this?
Any help is greatly apprecited.
Thanks a lot!
Elvira
1. Is it possible to delegate to multiple resources in PWA?
2. I am having issues with my projects not showing up correctly in Project
Center, it seems to have older versions. I've tried to republish a few times,
but this doen't help. Individuals can see the most recent tasks in their
"Tasks" menu, but not in the Project Center. If I open projects from the
Project Center using Project pro, it brings me to a correct updated project
plan, but if I try to look at it in PWA, it's an old version. Does anyone
know who to solve this?
Any help is greatly apprecited.
Thanks a lot!
Elvira