Delete all Time Sheets and Task and Projects

S

ss028955

We have installed Project Server 2007 on Test Server. I have played abound
with Time Sheets and Task and Projects. I just wanted delete all the
timesheets, All Task Sheets and projects and restart again. So I went to
"Delete Enterprise Objects" and Tried to delete that way but It sent me an
email below. Is there any other way to delete.

"Your ProjectDelete job failed. Its current state is FailedNotBlocking. It
was 8% complete. It entered the queue at 01/10/2008 14:20:00.

To get more information about the job failure, please go to Project Web
Access. Select Personal Settings from the left menu. Then select My Queued
Jobs.

The errors returned from the queue are as follows:
Error ID: 23006
Error ID: 26000

Detailed error below - send it to the administrator for more detailed
troubleshooting."
 
B

Bilal

Hi

the same happend to me and here are what I did to remove all the testing stuff
- If there is any timesheet which is created, you have to recall it and
delete it (both you can find them under Action menu item)
- I deleted the Timesheets periods then
- Then I checked out all the checked in projects
- Then I checked out all the checked in resource
- Then I deleted the projects
- Then the same thing I did for the resource


Best Regards

Bilal Okour
blog : http://ebilal.spaces.live.com
 
S

ss028955

Thanks for your help Paul and Billal. It is now working.

One additional step, Ihad to do for project was, I had to restart Microsoft
Office Project Server Queue Service when I tried to delet Projects.

Cheers
Sovana
 