Parris,
If the resources are assigned to tasks, view the Gantt chart use the
"using resource filter" to filter for those resources, and then
re-assign those tasks to other resources. After making sure the
resources have no tasks assigned, if you are using MS Project (not
Project Server), open the file, view the Resource Sheet and delete the
resources.
I sense there may be something more to what you need, but without
further information from you (are you using server? are you using a
resource pool file?) it's tough to give more specific advice.
I hope this helps. Let us know how you get along.
Julie
Project MVP
Visit
http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project