Hi All,
i deleted some task from a Adminstrative project and published the project,
but the assignments for the deleted tasks are still visible in the resource
timesheet that too without the big black cross mark that we usualy get when a
task is deleted of the project plan. Is there any way to find those tasks and
remove them from the timesheet. also i checked those assignments in the
msp_web_assignments table. the value of the WASSN_DELETED_IN_PROJ is still
'1' for the deleted assignments
i deleted some task from a Adminstrative project and published the project,
but the assignments for the deleted tasks are still visible in the resource
timesheet that too without the big black cross mark that we usualy get when a
task is deleted of the project plan. Is there any way to find those tasks and
remove them from the timesheet. also i checked those assignments in the
msp_web_assignments table. the value of the WASSN_DELETED_IN_PROJ is still
'1' for the deleted assignments