Syamal
In one of the projects, earlier I had assigned a resource with ceratin tasks.
Later, as a correction, I have mistakenly DELETED (not removed the
assignments) the resource from the relevant column in Project Pro and then I
published the project. After that, I have tried all 3 publish types (All,
republish, new/change) one after another, but still could not stop from
reappearing these assignments in PWA's resource assignment screen. While, In
Project Pro, in Gnatt chart view, it rightly shows this dis-association, but
PWA screen is not.
How to sync PWA with Project Pro, as far as these task assignments are
concerned? I should not delete this project nor this resource, as they have
other active assignment/tasks.
Thanks in advance for any effective help.
Later, as a correction, I have mistakenly DELETED (not removed the
assignments) the resource from the relevant column in Project Pro and then I
published the project. After that, I have tried all 3 publish types (All,
republish, new/change) one after another, but still could not stop from
reappearing these assignments in PWA's resource assignment screen. While, In
Project Pro, in Gnatt chart view, it rightly shows this dis-association, but
PWA screen is not.
How to sync PWA with Project Pro, as far as these task assignments are
concerned? I should not delete this project nor this resource, as they have
other active assignment/tasks.
Thanks in advance for any effective help.