"Deleted" Tasks in Project Server

T

The Flying PM

Hey Gang,

I've moved my first Project File ever into Project Server and I'm working to
get it set up so our team can use PWA for time reporting.

My question: I deleted two tasks in Project Professional, saved,
republished, etc. However, the tasks still show up to user. Albeit with a big
x. I could live with the big x, but when users export the tasks to Excel the
big x disappears and they look like other tasks.

Any way to make deleted tasks stop showing up in PWA?
 
J

JulieS

Hello Flying PM,

In the future, please post your questions concerning Project Server to
the Project Server newsgroup, not the "general questions" newsgroup.

To get you started on your question, see the following FAQ on the
Project Server Experts website at:
http://www.projectserverexperts.com/Shared Documents/deletecancelledtasks.htm

If you have a follow up questions, please post to the Server newsgroup.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional information
about Microsoft Project
 