Deleted Tasks Still showing in PWA

A

Ann Marie DeNeen

Hello,

Problem: Project manager deleted tasks in Project Pro and republished to
project server. The resource is still receiving overdue alerts and the tasks
are still showing in PWA for this resource. The tasks show that they were
removed but also say incomplete. Can someone tell us what we are doing wrong?

Thanks,

Ann Marie
 
G

Gary L. Chefetz [MVP]

Ann Marie:

What's happening is that PMs are deleting tasks from their project plan
without closing the assignments. You need to close-out the assignments by
setting the remaining work for each resource to zero. Then you need to
publish new and changed. At that point, you can safely delete the resources
from the task or delete the task. Note that if you delete tasks that have
actual work, you lose that work record. You can close out the work on a task
without deleting it if you care to preserve the entire project baseline.

--


Gary L. Chefetz, MVP
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server FAQS: http://www.projectserverexperts.com
For Project Server Books: http://www.projectserverbooks.com
For Project Server Training: http://www.projectservertraining.com
For Project FAQS: http://www.mvps.org/project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top