We have a situation where the PM deleted a task that had a resource assigned
to this task and the resource still had remaining work on this task. Since
there wasn't any actual time logged to the task by the resource, the PM was
able to delete the task but in PWA, the task is still showing up in the
resource's timesheet. How can we remove this deleted task from the resources
timesheet view?
to this task and the resource still had remaining work on this task. Since
there wasn't any actual time logged to the task by the resource, the PM was
able to delete the task but in PWA, the task is still showing up in the
resource's timesheet. How can we remove this deleted task from the resources
timesheet view?