M
MHGM
Actuals were incorrectly entered into future weeks (long story). The were
zeroed out and moved into the correct weeks. The PM who I am updating the
Program plan for said that the finish date of the task should be 4/11/05.
Currently, the finish date for the task is listed in project as 4/25/05.
When I try to move the task into 4/11, the ETCs are wiped out.
I think one issue could be the fact that when I zeroed out the incorrectly
entered actuals, "0 hrs" still appears in the Time Entry fields for the weeks
of 4/4, 4/11, and 4/18. Any way that I can truly blank out these Time
Entry fields, which I think would let me pull the Finish Date in?
Thanks.
zeroed out and moved into the correct weeks. The PM who I am updating the
Program plan for said that the finish date of the task should be 4/11/05.
Currently, the finish date for the task is listed in project as 4/25/05.
When I try to move the task into 4/11, the ETCs are wiped out.
I think one issue could be the fact that when I zeroed out the incorrectly
entered actuals, "0 hrs" still appears in the Time Entry fields for the weeks
of 4/4, 4/11, and 4/18. Any way that I can truly blank out these Time
Entry fields, which I think would let me pull the Finish Date in?
Thanks.