Deleting Actual Work Deletes Protected Actuals

A

Andrew

I am running Project Server 2007 with SP2 and Feb 2010 CU. I am using
the Task Setting Restrict Updates to PWA. However, when I delete all
the Actual Work for a resource in Project Pro, clicking Sync to
Protected Actuals does nothing. In addition, all the hours entered
via My Tasks of PWA are gone.

Has anyone else experienced this bug?
 
M

Martin Laukkanen

Hi Andrew,

Is your Project Professional client also running SP2 + CU? I have seen what
you mentioned but it was a bug that affected SP1 and I'm pretty sure it was
fixed before SP2...

Specifically the bug I recall was that it was possible in some cases to
delete an entire task with actuals despite there being actuals on the task
thus removing the protected actuals.
 
A

Andrew

Yes, the Project Professional client also has SP2 + Feb 2010 CU. My
version number is 12.0.6529.5000 SP2 MSO 12.0.6425.1000.

If I only remove some of the actual work hours, Sync to Protected
still works. But if I remove all actual work, Snyc to Protected
brings in nothing and all the hours are removed from My Tasks.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top