Deleting Projects - Timesheet Implications?????

A

anovak

I thought I was clearing out my test database when I deleted all
projects (but left enterprise resource pool intact).

Then I discovered there are timesheets still out there. What are the
implications and how should I clear all those out - the delete option
from PWA?

When a timesheet is deleted for a user, does it just set it back to
where they can create it again or is it gone forever?

Thanks,
Andy Novak
UNT
 
D

Dale Howard [MVP]

Andy --

When you delete Timesheets, the resets them as if the user never created the
Timesheet in the first place. Deleting projects, as you now know, does not
touch the Timesheets. Hope this helps.
 
A

anovak

Andy --

When you delete Timesheets, the resets them as if the user never created the
Timesheet in the first place. Deleting projects, as you now know, does not
touch the Timesheets. Hope this helps.

So, the timesheet will still show up as "to be created" by the user
then (looks as it did when I first configured timesheet periods as the
administrator)?
Thanks,
Andy
 
D

Dale Howard [MVP]

Andy --

Correct.




So, the timesheet will still show up as "to be created" by the user
then (looks as it did when I first configured timesheet periods as the
administrator)?
Thanks,
Andy
 