M
Mark Durrenberger
Here's an interesting thing I stumbled on last night.
I wanted to delete a task that was linked (predecessor/successor) to
adjacent tasks in the outline.
After the task was deleted, I wanted its predecessor and successor to be
linked (sort of like setting the 'middle' task to zero duration)
Anyone have a shortcut way of doing that?
I know I can write VB to do it... but the NG has been quiet lately so here
is something to chew on.
Mark
--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc, www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________
The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.
- Sir John Harvey-Jones
I wanted to delete a task that was linked (predecessor/successor) to
adjacent tasks in the outline.
After the task was deleted, I wanted its predecessor and successor to be
linked (sort of like setting the 'middle' task to zero duration)
Anyone have a shortcut way of doing that?
I know I can write VB to do it... but the NG has been quiet lately so here
is something to chew on.
Mark
--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc, www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________
The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.
- Sir John Harvey-Jones