Deliverables by the Hour

M

Mike Mahoney

Deliverables start and finish date information is in whole days,
regardles of the setting or the values in MSP. Is there a way to get
this down to an hourly level of detail?

Thanks

Mike
 
B

Ben Howard [MVP]

Hi Mike,
I don't think so. I suspect you have tried editing the deliverable date to
specify the hours?
 
B

Ben Howard [MVP]

I thougt it might be possible to change the date setting within a table entry
to show dd/mm/yy hh:mm, and then show the deliverable start/finish dates
within the table, however the start/finish dates are not editable within
Project Pro; my conclusion is the same as yours - not possible.
 