M
Manis
This is a problem that I'm having in my project.
The project plan was complete and we had all the dependencies set. Many of
them were start to finish. Now during the project, I'm finding that many of
the successor tasks are actually complete before the predecessor!
I understand that the dependencies were setup wrong. The users say that the
dependencies are actually resource dependent instead of task dependencies.
For eg:- if a task is being executed by an experienced resource, he has the
required knowledge and does not have to wait for the predecessor to be
complete. Valid argument. The problem is that the task has a generic resource
against it. So, at the time of planning, I don't know what kind of dependency
to set. I elected to use "start to finish". (Don't ask why.)
Question : If a successor is set as complete before the predecessor, what
happens to the dates?
if Task1, Task2 & Task3 are to be executed in that sequence and I mark Task2
as complete before Task1, what happens to the plan for Task1 and Task3?
The project plan was complete and we had all the dependencies set. Many of
them were start to finish. Now during the project, I'm finding that many of
the successor tasks are actually complete before the predecessor!
I understand that the dependencies were setup wrong. The users say that the
dependencies are actually resource dependent instead of task dependencies.
For eg:- if a task is being executed by an experienced resource, he has the
required knowledge and does not have to wait for the predecessor to be
complete. Valid argument. The problem is that the task has a generic resource
against it. So, at the time of planning, I don't know what kind of dependency
to set. I elected to use "start to finish". (Don't ask why.)
Question : If a successor is set as complete before the predecessor, what
happens to the dates?
if Task1, Task2 & Task3 are to be executed in that sequence and I mark Task2
as complete before Task1, what happens to the plan for Task1 and Task3?