A
AC
MS Project 2000 keeps messing it all up and I cannot for the life of me
figure out why. I've got a bunch of sub-tasks that are all linked
end-to-start. I'll try to explain:
A
->B
->->C
->->D
->->E
->F
C, D and E are children of B; F is a successor of B; C, D and E are all
linked end-to-start.
I keep adding into the list containing C, D and E as the project goes
on. For some reason, F is now not starting when E finishes. If I add
task G as a child of B, successor to E, I get a conflict error - "Task
G has a task constraint or is linked to a task that cannot move, and as
a result the constraint or the link cannot be set. (Cancel/continue)"
It highlights the dependency in task F.
I notice that task F's start date is set to task E's start date
(whether coincidence or not I have no idea.)
If I unlink C, D and E, I'd expect their start dates to go back to the
project start date but they don't. Maybe by setting them to complete,
I've set the end date??? How do I undo fixed dates?
Any ideas? I'm flummoxed.
Thanks for your time,
AndyC
figure out why. I've got a bunch of sub-tasks that are all linked
end-to-start. I'll try to explain:
A
->B
->->C
->->D
->->E
->F
C, D and E are children of B; F is a successor of B; C, D and E are all
linked end-to-start.
I keep adding into the list containing C, D and E as the project goes
on. For some reason, F is now not starting when E finishes. If I add
task G as a child of B, successor to E, I get a conflict error - "Task
G has a task constraint or is linked to a task that cannot move, and as
a result the constraint or the link cannot be set. (Cancel/continue)"
It highlights the dependency in task F.
I notice that task F's start date is set to task E's start date
(whether coincidence or not I have no idea.)
If I unlink C, D and E, I'd expect their start dates to go back to the
project start date but they don't. Maybe by setting them to complete,
I've set the end date??? How do I undo fixed dates?
Any ideas? I'm flummoxed.
Thanks for your time,
AndyC