Dependency Arrows

P

Philg

Hi I have created my schedule and baselined it. I've added a legend so that I
can demonstrate baseline milestone dates versus current forecast dates.
The dependency arrows still point at the baseline milestones, could you
explain how I can show the dependencies against the current planned dates an
not at the baselines. Thank you..
 
P

Projectability

Philg,

I have checked my version of Project and the dependency links show from the
curent schedule and not the baseline, if I change the schedule the links
point to the current scheduled tasks and milestones not the baseline.

The links are shown from the first defined bar style in the Bar Styles
dialogue box - if you cut a row definining a bar style that was listed in
2nd or 3rd position and paste it in to the first row in the dialogue box the
display will then show the links going from this bar style.

--
Dominic Moss

Projectability - Helping People achieve more with Microsoft Project

Check the Downloads section on our Website for useful documents on both
Project Management and Microsoft Project

www.projectability.co.uk

Why not subscribe to our monthly newsletter for hints tips and views

http://visitor.constantcontact.com/manage/optin/ea?v=001WVdpo956d6lHqIISFtfgVw==
 