K
Kesari Suresh
Hi ,
I was trying to check dependency on tasks that are linked to each other.
1. Initiall i created two tasks. First task was scheduled from 01/08/2006 to
03/08/2006, second task was scheduled from 04/08/2006 to 06/08/2006. Both the
tasks to assigned to same resource.
2. I defined a constraint on second task giving first task as its
predecessor and applies Finish to Start. Then i clicked on task advanced
properties and have chosen start no earlier than 03/08/2006 for second task.
3.THen i logged in with the resource id and completed task 2 and sent an
update to project manager.
4. Project manager accepted the task and clicked update to project, which
opened ms professional and updated the task status to complete.
5.I dont know why the constratint is not being applied here. Please help me
6. Another scenario is that i tried to complete the task at an earlier date
and sent
for pm approval, which the pm accepted.
7. When the task status is getting updated in ms professional i got a
warning saying that the task date should be readjusted for which the pm said
no and cancelled the operation.
8. after cancelling the task updates in ms professional how can the user get
back his task. The pm is not able to change the task status to reject now/
How can a accepted task be given back to the user again when task changed
have not been made at ms professional?
Please help me in this ragard.
I was trying to check dependency on tasks that are linked to each other.
1. Initiall i created two tasks. First task was scheduled from 01/08/2006 to
03/08/2006, second task was scheduled from 04/08/2006 to 06/08/2006. Both the
tasks to assigned to same resource.
2. I defined a constraint on second task giving first task as its
predecessor and applies Finish to Start. Then i clicked on task advanced
properties and have chosen start no earlier than 03/08/2006 for second task.
3.THen i logged in with the resource id and completed task 2 and sent an
update to project manager.
4. Project manager accepted the task and clicked update to project, which
opened ms professional and updated the task status to complete.
5.I dont know why the constratint is not being applied here. Please help me
6. Another scenario is that i tried to complete the task at an earlier date
and sent
for pm approval, which the pm accepted.
7. When the task status is getting updated in ms professional i got a
warning saying that the task date should be readjusted for which the pm said
no and cancelled the operation.
8. after cancelling the task updates in ms professional how can the user get
back his task. The pm is not able to change the task status to reject now/
How can a accepted task be given back to the user again when task changed
have not been made at ms professional?
Please help me in this ragard.