Hi,
I'm just trying find a way to have actual status of milestones in the
master project plan. I create deliverables on sub projects and add a
dependenxy of milestone in the mastert to one of them. But it gives
nothing. As far as I understood it's not automaticall shift the dates when
you add a depndency for external deliverable. Do I need to use "ghost"
tasks as it was with 2003 to have an actual pdated information for
milestones in master plan? What for this deliverables in this case?
TIA
Best regards,
Alexander Barvinsky
I'm just trying find a way to have actual status of milestones in the
master project plan. I create deliverables on sub projects and add a
dependenxy of milestone in the mastert to one of them. But it gives
nothing. As far as I understood it's not automaticall shift the dates when
you add a depndency for external deliverable. Do I need to use "ghost"
tasks as it was with 2003 to have an actual pdated information for
milestones in master plan? What for this deliverables in this case?
TIA
Best regards,
Alexander Barvinsky