dependent project

S

shima

hi;
i wanna define a project that its start date is dependent on an external
task that i dont know its exact delivering time.so when i wanna define it
according my planning,if that task delivering time changes,my planning gantt
chart will change.i need to idendify this dependency and i dont know how.
please help me;
thanka alot.
 
M

Mike Glen

Hi Shima,

Welcome to this Microsoft Project newsgroup :)

You must make a best estimate of the start date. Then when you know, you
can run the Adjust_Dates macro in the Analysis toolbar, or change to the new
start date you enter in Project/Project Information.

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 