C
Chris Gray
Does anyone know how (if it is possible) to setup dependent resources in
microsoft project server 2003 (or project professional)
Example
I have 2 trucks and 3 truck drivers in my enterprise resource pool
I want to setup project so that when I assign a truck to a task Project
automatically adds a truck driver if one is available
I should not be able to assign a truck if no driver is available
Any ideas ?
Chris
microsoft project server 2003 (or project professional)
Example
I have 2 trucks and 3 truck drivers in my enterprise resource pool
I want to setup project so that when I assign a truck to a task Project
automatically adds a truck driver if one is available
I should not be able to assign a truck if no driver is available
Any ideas ?
Chris