C
Clive
Hi,
I have two tasks. Task one must complete 2 weeks before Task 2 can complete
and they both have same start time. How do I link these tasks so that a delay
in task 1 will push out finish date of task 2?
Thanks.
I have two tasks. Task one must complete 2 weeks before Task 2 can complete
and they both have same start time. How do I link these tasks so that a delay
in task 1 will push out finish date of task 2?
Thanks.