B
Ben
Hi all,
This has me stumped, so any help/suggestions would be greatly
appreciated. The scenario I need to enable is this:
1. The PM assigns a 20h Task to a team of people, not knowing who will
actually be doing the work.
2. Team Member A does 12h work on the Task and Team Member B does 6h.
They both submit status updates back to the PM.
3. The PM approves the two updates and the plan now shows Remaining
Work as 2h.
The above scenario may sound straightforward but I can't seem to
configure Project to enable this.
- Using Team Resources allows the PM to assign the Task appropriately,
but the Task doesn't appear in Team Member's My Tasks unless they
specifically 'Self-assign team tasks'. When they do, and it's approved
by the PM, the Resource Assignment changes to their name. If Team
Member B wants to add hours to that task as well, they need to
manually add a new task to their My Tasks and find the Task. But the
real problem is that when they add their 6h to the Task, the overall
work becomes 26h (i.e. the original 20h stays with Team Member A so
Team Member B's 6h work is in added to the Task's work.)
- I tried manually listing both resources against the task (i.e. not
use Team Resources feature) and put 10h against each resource. Team
Member A has done 12 hours instead of their allocated 10h, so the
total work for the task becomes 22h instead of 20h (with Team Member B
listed as having 4h remaining)
I'd like the overall work to remain at 20h. Is this possible? Does
anyone have suggestions on other approaches I could try?
Many thanks,
Ben
This has me stumped, so any help/suggestions would be greatly
appreciated. The scenario I need to enable is this:
1. The PM assigns a 20h Task to a team of people, not knowing who will
actually be doing the work.
2. Team Member A does 12h work on the Task and Team Member B does 6h.
They both submit status updates back to the PM.
3. The PM approves the two updates and the plan now shows Remaining
Work as 2h.
The above scenario may sound straightforward but I can't seem to
configure Project to enable this.
- Using Team Resources allows the PM to assign the Task appropriately,
but the Task doesn't appear in Team Member's My Tasks unless they
specifically 'Self-assign team tasks'. When they do, and it's approved
by the PM, the Resource Assignment changes to their name. If Team
Member B wants to add hours to that task as well, they need to
manually add a new task to their My Tasks and find the Task. But the
real problem is that when they add their 6h to the Task, the overall
work becomes 26h (i.e. the original 20h stays with Team Member A so
Team Member B's 6h work is in added to the Task's work.)
- I tried manually listing both resources against the task (i.e. not
use Team Resources feature) and put 10h against each resource. Team
Member A has done 12 hours instead of their allocated 10h, so the
total work for the task becomes 22h instead of 20h (with Team Member B
listed as having 4h remaining)
I'd like the overall work to remain at 20h. Is this possible? Does
anyone have suggestions on other approaches I could try?
Many thanks,
Ben