Sandy
We use Project Server 2007 for enterprise projects. Project Pro 2007 help
says oone cane "Change the status manager - Other proejct managers can become
the status manager for any of the proejct's tasks. For example, one project
manager might identify another as the status manager to cover absense. The
status manager takes ownership of the task assignments, so as to receive all
status updates while the project manager is absent." When I tried to assign
a status manager to selected tasks on an enterprise plan, only the project
manager's name assigned to that project was in the drop down from which the
status manager could be selected. How can I add other [enterprise] project
managers to the status manager drop down field?
says oone cane "Change the status manager - Other proejct managers can become
the status manager for any of the proejct's tasks. For example, one project
manager might identify another as the status manager to cover absense. The
status manager takes ownership of the task assignments, so as to receive all
status updates while the project manager is absent." When I tried to assign
a status manager to selected tasks on an enterprise plan, only the project
manager's name assigned to that project was in the drop down from which the
status manager could be selected. How can I add other [enterprise] project
managers to the status manager drop down field?