U
Uval Blumenfeld
Hi,
I'm trying to detect which tasks have been changed in a project.
ProjectBeforeTaskChange is insufficient because it isn't fired when a
dependency causes a task to slip. I have looked at the field "Update Needed"
on the task, but this value doesn't seem to change if I'm not connected to
project server... Can anyone point me in the right direction?
thanks in advance,
Uval
I'm trying to detect which tasks have been changed in a project.
ProjectBeforeTaskChange is insufficient because it isn't fired when a
dependency causes a task to slip. I have looked at the field "Update Needed"
on the task, but this value doesn't seem to change if I'm not connected to
project server... Can anyone point me in the right direction?
thanks in advance,
Uval