R
Riko Wichmann
Dear all,
I need to implement the following scenario:
I have an *external* milestone "M1: final system available". This
external milestone links into a plan defining and setting up and running
the test environment. M1 defines (externally), when the tests have to be
finished. Let's say, my (test environment) plan contains a task "T1:
system test".
Now, the end date of T1 cannot be later than M1. How do I implement
that, so that
1) I get a warning, when my planning causes the Finish Date of T1 to be
later than M1 (this one could easily accomplish with a deadline)
2) warning, if (the external) M1 moves to earlier date, so that as a
result T1 would now be too late, while before the adjustment of M1 it
was just in time.
I toyed around with various constraints and task dependencies without
success. The easiest would be to feed a deadline on T1 with the date of
M1, but that can only be done "by hand" I assume ...
We are using Project 2007 (Enterprise).
Any hints or ideas would be much appreciated.
Thanks and cheers,
Riko
PS: I posted this question also on the microsoft.public.project group,
but one suggested to also try here, since all our project are on an
Enterprise server.
I need to implement the following scenario:
I have an *external* milestone "M1: final system available". This
external milestone links into a plan defining and setting up and running
the test environment. M1 defines (externally), when the tests have to be
finished. Let's say, my (test environment) plan contains a task "T1:
system test".
Now, the end date of T1 cannot be later than M1. How do I implement
that, so that
1) I get a warning, when my planning causes the Finish Date of T1 to be
later than M1 (this one could easily accomplish with a deadline)
2) warning, if (the external) M1 moves to earlier date, so that as a
result T1 would now be too late, while before the adjustment of M1 it
was just in time.
I toyed around with various constraints and task dependencies without
success. The easiest would be to feed a deadline on T1 with the date of
M1, but that can only be done "by hand" I assume ...
We are using Project 2007 (Enterprise).
Any hints or ideas would be much appreciated.
Thanks and cheers,
Riko
PS: I posted this question also on the microsoft.public.project group,
but one suggested to also try here, since all our project are on an
Enterprise server.