Riko Wichmann
Dear all,
I need to implement the following scenario:
I have an *external* milestone "M1: final system available". This
external milestone links into a plan defining and setting up and running
the test environment. M1 defines, when the tests have to be finished.
Let's say, my plan contains a task "T1: system test".
Now, the end date of T1 cannot be later than M1. How do I implement
that, so that
1) I get a warning, when my planning causes the Finish Date of T1 to be
later than M1
2) warning, if M1 moves forward, so that as a result T1 would be too late.
I toyed around with various constraints and task dependencies without
success. The easiest would be to feed a deadline on T1 with the date of
M1, but that can only be done "by hand" I assume ...
We are using Project 2007 (Enterprise).
Any hints or ideas would be much appreciated.
Thanks and cheers,
Riko
I need to implement the following scenario:
I have an *external* milestone "M1: final system available". This
external milestone links into a plan defining and setting up and running
the test environment. M1 defines, when the tests have to be finished.
Let's say, my plan contains a task "T1: system test".
Now, the end date of T1 cannot be later than M1. How do I implement
that, so that
1) I get a warning, when my planning causes the Finish Date of T1 to be
later than M1
2) warning, if M1 moves forward, so that as a result T1 would be too late.
I toyed around with various constraints and task dependencies without
success. The easiest would be to feed a deadline on T1 with the date of
M1, but that can only be done "by hand" I assume ...
We are using Project 2007 (Enterprise).
Any hints or ideas would be much appreciated.
Thanks and cheers,
Riko