Hello,
We have recently installed MSP Server / Pro 2003 with 1500 resources in the
global resource pool and 600 projects
When viewing the Resource Usage sheet, or runing Cash Flow Reports the costs
include the cost for "Resource A" working on the project that is open, as
well as all the other projects they are working on in Project Server. We are
trying to determing the costs for only the Project we have open at the time.
(ie leave out all the other <project name.published> projects the resource is
working on.)
Is there any way to do this workaround?
I apologise if you have answered this question elsewhere (please point me to
the place), I'm new to this game and have posted it to somewhere I can't find
it! 3 hours of searching today without success.
Thank you for your help.
We have recently installed MSP Server / Pro 2003 with 1500 resources in the
global resource pool and 600 projects
When viewing the Resource Usage sheet, or runing Cash Flow Reports the costs
include the cost for "Resource A" working on the project that is open, as
well as all the other projects they are working on in Project Server. We are
trying to determing the costs for only the Project we have open at the time.
(ie leave out all the other <project name.published> projects the resource is
working on.)
Is there any way to do this workaround?
I apologise if you have answered this question elsewhere (please point me to
the place), I'm new to this game and have posted it to somewhere I can't find
it! 3 hours of searching today without success.
Thank you for your help.