M
Mark VII
Greetings -
We need to be able to answer the question of "what percent complete do we
need in order to be on schedule as of a specified date", but I don't see a
way to get this directly from Project at the summary task or project level.
The software is obviously doing something internally because the status field
shows values of "on schedule" vs "late", based on the % complete field.
At the individual task level, I was able to work something up at the
individual task level based on duration and time elapsed since task start.
Basically, the formula is ([report date] - [task start date])/([duration]).
Where I'm having difficulty is computed the needed percent complete at some
level of summary. In our case, this is not only for subtasks, but also based
on groupings of tasks that don't neatly fall into the outline structure (long
story).
Does anyone have any suggestions?
Thanks in advance,
Mark
We need to be able to answer the question of "what percent complete do we
need in order to be on schedule as of a specified date", but I don't see a
way to get this directly from Project at the summary task or project level.
The software is obviously doing something internally because the status field
shows values of "on schedule" vs "late", based on the % complete field.
At the individual task level, I was able to work something up at the
individual task level based on duration and time elapsed since task start.
Basically, the formula is ([report date] - [task start date])/([duration]).
Where I'm having difficulty is computed the needed percent complete at some
level of summary. In our case, this is not only for subtasks, but also based
on groupings of tasks that don't neatly fall into the outline structure (long
story).
Does anyone have any suggestions?
Thanks in advance,
Mark