Developing Tasks into Project Server.

S

SQL

Hi,

I have project server 2003 installed and ready to go. I have a project file
that will be shared by a group of users, and now I want to programmatically
inserts tasks into this project file and have it update to project server.

Can anyone point me in the right direction to getting started.

Thanks.
 
E

Earl Lewis

Hi SQL,

Programatically inserting tasks can be done a couple ways. Using PDS is one of them. You can find info on PDS on the M$ website.

One important note: Even though tasks can be added via PDS, project pro (client-side app) contains all the scheduling application logic so projects need to be opened and schedules calculated from project pro for task inserts to be useful.

Earl
Hi,

I have project server 2003 installed and ready to go. I have a project file
that will be shared by a group of users, and now I want to programmatically
inserts tasks into this project file and have it update to project server.

Can anyone point me in the right direction to getting started.

Thanks.
 