slawlor
Hello,
I am working in MS Project 2007 and saving a copy in MS Project 2003 format
for another person to review.
Where a resource has a vacation set in their resource calendar, 2003 shows
more progress than 2007 on the Gantt chart.
Even if I look at the 2003 format file in 2007, I see the same progress as
the 2007 format. But if I look at the 2003 file in 2003, I see different
progress from the original.
Any ideas?
Steve