Difference between Timesheet Cube & MSP_Project_Timesheet cubes

V

Vinod Shenoy

Hi All,

We are using MS Project Server 2007. I would like to know why there is a
difference in Actual Hours reported by Timesheet Cube & MSP_Project_Timesheet
cubes? Can this difference be avoided?
 
G

Gary Chefetz

Vinod:

The Timesheet Cube shows actual work reported through the timesheet. The
MSP_Project_Timesheet shows actual work recorded in the Project file. There
are numerous reasons why these would not be in sync, including bugs in the
Project client that have just recently been resolved in the December 2009
CU. With that said, bugs are the least common reason for discrepancies
unless you're using the Project Server setting to restrict updates to actual
work from Project Web Access only, which locks down the system rather
tightly and not a practical option for many organizations.

So for example: Suppose a PM updates a task status directly in the project
plan where a resource is assigned. This imputes actual work that will never
show in the timesheet cube. As this is a very common practice, in many, if
not most cases, you are very likely to see more actual work registered in
the project plan than in the timesheets, unless of course, your PMs are also
in the habit of deleting completed tasks, which would have the exact
opposite impact.
 
V

Vinod Shenoy

Gary,
Thank you for the reply. Can I conclude that only Timesheet cube will hold
the correct Timesheet data? And is it safe to write a query in Reporting DB
which joins Timesheet data and UserViews?
 
G

Gary Chefetz

As long as you're capturing all time through the TS system, then yes, this
is your single source of reliable time information. BTW, this exchange
inspired me to write a blog post on this topic.
 