Difference in behavior or ProjectPercentCompleted andProjectPercentWorkCompleted?

A

anovak

I'm sure of the implications, but not sure about how these two
attributes actually differ from each other in behavior in project
server. Are they basically the same? When would you use one
column over the other in the reporting database?

Thanks,
Andy Novak
UNT
 
D

Dale Howard [MVP]

Andy --

These two fields correspond with the Percent Complete field and the Percent
Work Complete fields you see in Microsoft Project. Percent Complete refers
to the percentage of the Duration completed for a task or for the project,
and is calculated using the formula:

Percent Complete = Actual Duration/Duration

Percent Work Complete refers to the percentage of Work completed for a task
or for the project, and is calculated using the formula:

Percent Work Complete = Actual Work/Work

Depending on how a project manager tracks progress in a project, the Percent
Complete and Percent Work Complete fields might contain identical numbers,
or totally different numbers. Hope this helps.
 