Differences between Project 2002 & 98

A

Angela

Does anyone know what you loose if you take a Project 2002 schedule and save
it back to a Project 98 file? Here's my problem. I have a large schedule
that was created in Project 98. I then did some additional work in Project
2002, and saved it back as a 98 file. Now whenever anyone works in the file
using Project 98, the % complete on many summary tasks go to 0% even though
there are items in progress.

Thanks,
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top