Hi Sondin,
Let me try to clarify a bit further.
First, in your explanation of fixed work, you say "the task is 4 days".
That is ambiguous; do you mean there is 4 mandays of Work on the task or do
you mean the task wil last for 4 days?
Remamber, Work is mandays, Duration is the time during which any work is
delivered.
When a resoruce works halftime (units 50%) on a task during 6 days, its
worek will be 3 mandays.
As a general rule also, the task type ONLY comes into play when you MODIFY
an existing assignment
This being said, you say:
Fixed duration will not change the duration of the task even if you add more
resources to this task.
Right, but not complete, this is the complete statement:
Fixed duration will not change the duration of the task even if you add more
resources to this task (by increasing the assignment units) , nor when you
increase the amount of work to be done.
Fixed work: first, let's stick to 1 resource per task fore the basic
explanation, that's complex enough as it is.
On a fixed work task, when you change duration or assignment units, work
will remain constant and its's the 3rd parameter that will adapt to keep
work=duration*units.
Fixed units: when you say somebody is assigned 50% on a task, changing work
or duration will not change that. Changing work will modify duration and
vice versa.
Hope this helps,
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf