Different calendars Project server/pro 2003

R

Rasaglez

Hi,
I have in the enterprise global a base calendar named "Estandar" (8am ..12pm
and 1pm to 5pm), and also my resources use this calendar.

The problem is that I have some projects that were imported to the project
server with a differente calendar named "standard" (9am..1pm and 2pm to 6pm).

There are resourses (Estandar calendar) asigned to the projects with
"Standard" calendar. The problem is that if I have linked tasks (Finish to
Start), the duration is 1 day, but the Star is 9/dec/07 and Finish is
10/dec/07. When I see the view of Task usage I found that tue work is 1hr
9/dec/07 and 7hr 10/dec/07 because the predecesor task has less than 8hrs of
work.

For my company we work with complete days of 8 hrs, we do not use decimal
days (ex. 1.3day)

What can I do?

Also I trying to change calendars but it does not work. And sometimes when I
try to add a resource from the resource pool, project show me a message that
said something that I need to synchronize the project pro calendar with the
project server calendar. (How can I do for do this when this process is not
automátic?)

Thank you for your answers!!

You can write me to: (e-mail address removed)
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top