Hello,
I'm running into an issue with reporting time from my timesheet in my
Outlook Addin.
There is a task that I have assigned that has 16hrs baseline. I have
assigned 8hours yesterday and 2 hours today on the task, bringing the total
to 10. I have Specified "Remaining Work" to 4hours. I saved the work to
Project Server and have submitted it to the PM (which is me).
I accepted the updates from the timesheet and updated the project in Project
2007. However, the task now shows 13hours worked and 100% complete.
How on earth does that happen? :|
I have deleted the task and tried to reclaim the proper state with the same
results. Is there something horribly obvious about this process that I'm
overlooking?
Thank you,
Michael
I'm running into an issue with reporting time from my timesheet in my
Outlook Addin.
There is a task that I have assigned that has 16hrs baseline. I have
assigned 8hours yesterday and 2 hours today on the task, bringing the total
to 10. I have Specified "Remaining Work" to 4hours. I saved the work to
Project Server and have submitted it to the PM (which is me).
I accepted the updates from the timesheet and updated the project in Project
2007. However, the task now shows 13hours worked and 100% complete.
How on earth does that happen? :|
I have deleted the task and tried to reclaim the proper state with the same
results. Is there something horribly obvious about this process that I'm
overlooking?