Different cost rates, one resource pool, cost rate table insuffici

A

AntonyS

As well as planning and scheduling we use Project to calculate the cost of a
project. Our projects will have a number of different resources with
different hourly cost rates. Those same resources work on another project
with a totally different set of hourly costs. This works great when the
projects are on their own but I would like to use the resource pool
functionality for scheduling. Doing so means that I can have only one cost
price unless I use rate tables - rate tables only allow 5 rates I need more.
I will aslo need to change a large number of project plans. Is there an
alternative?
 
R

Rod Gill

Not with a resource pool. Alternative is:

No pool
use separate rates as needed.
Weekly create a new consolidated project but deselect Link when inserting
each project. This copies all info and consolidates resource workload across
all projects. You will only get a single resource rate in the master
project, but I guess you need this for levelling?

Work out what each PM needs to do to adjust their resource usage. Master
provides good snapshot across all projects each week. Can record a macro to
make creating new master each week quick and easy.
 
J

Jan De Messemaeker

Hi,

Yes.
When connecting the files to the ppol select
Sharer takes precedence
In that case in each project the specific rates for THAT project will be
used;
HTH
 
A

AntonyS

Hi Jan,

This works to an extent - this is what I tried.

I created a new resource pool, put three resources in it. I created a
project file called file A and created some activities and costs, linked to
the resource pool with sharer as presedence. The total cost for File A was
£2800. I created a new File B connected to the resource pool, added some
activities and costs and resourced the activities - again saved with sharer
as presendence. The costs for File B came to £5120. If I open one file, work
with it, close it etc all the cost information is fine - this is great.
However if I open File A, then File B, save and close File B I find that File
B has had File A's costs written to it. Do you know if I would have this same
problem over a network, i.e. If Project ManagerA has File A open and then
Project Manager B opens saves and closes file B?
 
A

AntonyS

Hi Rod,

Thanks for this. Unfortunately there are a number of Project Managers who
require real time access to the resource pool so a weekly update is not
appropriate. Would you know if Project Enterprise handles this better?
 
J

Jan De Messemaeker

Hi,

1. Did you change the unit costs in A and B before saving them again? I
thought that was the point, to have different unit costs for the same
resoruces; you only mention ytotal cost which i can not possibly interpret.

2. If you see A's costs in B and vice versa you somehow messd things up with
a save as; Project would never do that. Working locally or on a server
doesn't change the behaviour.

3. Maybe you mean B shows A's costs AS WELL, on top of its own? Close the
pool and each project only shows its own costs.

Hope this helps,
 
A

AntonyS

Hi Jan,

thanks for the information and your patience, its appreciated!

The unit costs in A and B are different. Here's what I have just tried...

If I open Plan A and the resource pool (the resource pool is in read only
mode), the resource pool / resource sheet / entry view displays the hourly
costs for the resources in Plan A.

Keeping Plan A and the resource pool open, if I then open Plan B and look at
the resource pool / resource sheet / entry view the view updates and displays
the hourly costs for the resources in Plan B.

If I then add a new task line to Plan A using a resource that is in Plan A
and Plan B it uses the cost information from Plan B not Plan A.

Just for fun - if you have all three files open and then tile the view you
can update the hourly cost of a resource in Plan A or Plan B and watch as it
immediately updates the other open files. Closing the resource pool stops
this update from rippling across.
 
J

Jan De Messemaeker

Hi,

Hi,

I can understand the lmogic of the guy who programmed this - weird but there
is a logic- but the main thoing is you have your solution.
When the pool is closed each project uses its own rates.
Hope this helps,
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top