I tried to fix my first post so maybe it will make more since. On every trip
I need the total in each row to update. So the total for Site
Preparation after the first trip needs to be 2%, on the secound Trip it needs
to be 100%. Same for the other rows.
Framing 2nd Trip the total needs to be 24%
3rd Trip the total needs to be 36%
4th Trip the total needs to be 84%
Plumbing 3rd Trip the total needs to be 2%
4th Trip the total needs to be 4.8 round to 5%
I know the formula to get the percentage but how do I get it to update after
the next trip?
Jan Feb Mar AprValue 1 2 3 4
TOTAL
I need the total in each row to update. So the total for Site
Preparation after the first trip needs to be 2%, on the secound Trip it needs
to be 100%. Same for the other rows.
Framing 2nd Trip the total needs to be 24%
3rd Trip the total needs to be 36%
4th Trip the total needs to be 84%
Plumbing 3rd Trip the total needs to be 2%
4th Trip the total needs to be 4.8 round to 5%
I know the formula to get the percentage but how do I get it to update after
the next trip?
Jan Feb Mar AprValue 1 2 3 4
TOTAL