different hours on different days

P

Parag Lawate

my requirement is to have plan per resource as given below:-

day1 - 4 hrs on task1
day2 - 3 hrs on task1
day3 - 5 hrs on task1 etc

how to achieve this without changing setup frequently
thank u
 
D

Dave

Parag said:
my requirement is to have plan per resource as given below:-

day1 - 4 hrs on task1
day2 - 3 hrs on task1
day3 - 5 hrs on task1 etc

how to achieve this without changing setup frequently
thank u

Since there is no algorithmic way that Project can know that (short of
reading your mind), you will have to enter that work contour manually.
 
J

Jan De Messemaeker

Hi,

Since your identiacl posts on Feb 6 and another one earlier, there has not
been a new version of Project and we do not expect one any day now, so it
seems a bit useless to repeat the same question several times.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 