Different number of hours in Actual and Actual Work Protected Fiel

A

Anatoly Tarasov

Hi all!
I know that sometime, when you have some wrong Actual work hours (not the
same as Actual Work Protected), you can synchronise those to Actual Work
Protected through Tools >> Tracking >> Sync to Protected Actuals, but now I
have an extremely different numbers in Actual and Actual Work Protected with
almost 1000 hours difference (for one task Actual is 74 hours and Protected
is 899.18 hours). Synchronising does not make any difference, because
actually the data is correct, however somehow is displayed wrong in MS
Propject. I have checked this data extracting both Actual and Protected
straight from the database and there I see that actually everything is
correct (for this example task both Actual and Protected is 74 hours), but I
can not understand why it's displayed wrong in MS Project.
Maybe someone knows the anser to this mystic occurance?
 