kevmcdonk
I think that I know the answer to this question but I want to confirm
before I commit to the user.
Is there anyway to set up Project Server 2003 so that a project manager
can make changes to a resource's rate that will only affect the
resource for that project and will also be saved? Currently if a
Project Manager changes the rate, an error pops up saying that the
value is set at the Enterprise level and will not be saved.
having to set up all the individual rates for the Project Managers'
resources which is certainly not ideal. We would much rather leave it
up to the inidividual Project Managers.
Many thanks in advance,
Kev
before I commit to the user.
Is there anyway to set up Project Server 2003 so that a project manager
can make changes to a resource's rate that will only affect the
resource for that project and will also be saved? Currently if a
Project Manager changes the rate, an error pops up saying that the
value is set at the Enterprise level and will not be saved.
the Resource Information but that would involve our administratorFrom other posts, I've seen that you can set up different cost rates in
having to set up all the individual rates for the Project Managers'
resources which is certainly not ideal. We would much rather leave it
up to the inidividual Project Managers.
Many thanks in advance,
Kev