A
Angie
I need help!
1. I've created several PWA Project Center custom views.
Is there a way to have a different timescale for these custom views.
2. Also, my enterprise global settings are middle tier= years, bottom
tier= weeks.
This timescale appears correctly in Project Pro, but not PWA.
In PWA, I get middle tier in weeks and bottom tier in days! Also
weekends and holidays are not showing as non working time.
Help
1. I've created several PWA Project Center custom views.
Is there a way to have a different timescale for these custom views.
2. Also, my enterprise global settings are middle tier= years, bottom
tier= weeks.
This timescale appears correctly in Project Pro, but not PWA.
In PWA, I get middle tier in weeks and bottom tier in days! Also
weekends and holidays are not showing as non working time.
Help