Different Timescales per Custom View? PWA Timescale

A

Angie

I need help!
1. I've created several PWA Project Center custom views.
Is there a way to have a different timescale for these custom views.

2. Also, my enterprise global settings are middle tier= years, bottom
tier= weeks.
This timescale appears correctly in Project Pro, but not PWA.
In PWA, I get middle tier in weeks and bottom tier in days! Also
weekends and holidays are not showing as non working time.
Help
 
D

Dale Howard [MVP]

Angie --

1. Unfortunately, you cannot preset the level of zoom on the timescale in
Project Center views.
2. See #1 above. You cannot create a custom timescale in PWA the way you
can in Project Professional.

Hope this helps.
 