S
Sasha
I have a task which carries on over a long-ish period.
During that time, a resource will spend some time working
on it, and some time not working on it. I can show that
by splitting the task.
But can I show the resource utilisation at different % at
different times? EG: week 1 - 100%, week 2 - off, week 3 -
50%.
The problem I have is that if there is a single
utilisation % throughout, then the resource is
overallocated on the Resource Graph when it is allocated
to other tasks. And I'm trying to avoid having separate
tasks for every time the resource stops and starts the
job, though this may be the only solution?
Any help will be appreciated!
During that time, a resource will spend some time working
on it, and some time not working on it. I can show that
by splitting the task.
But can I show the resource utilisation at different % at
different times? EG: week 1 - 100%, week 2 - off, week 3 -
50%.
The problem I have is that if there is a single
utilisation % throughout, then the resource is
overallocated on the Resource Graph when it is allocated
to other tasks. And I'm trying to avoid having separate
tasks for every time the resource stops and starts the
job, though this may be the only solution?
Any help will be appreciated!