Hello,

At PWA (2007) I see a different values at project view compared with My task
view. for example: % work complete ect.

Any idea ?

Thanks

P.
 
R

Ray McCoppin

My Task page is really your assignments to tasks. So if more than one person
is assigned to a task the numbers in the proect detail will be different than
that is in My Tasks. For example if tow resources are assigned to a task
that has 40 hours work and one reports 20 hours of actual work and 100%
complete the task is only 50% complete.

Hope this helps
--
Ray McCoppin

http://www.randsmanagement.com
Project Server 2007 Automation Tools
Project Server 2007 Archive Tool
SRS gantt charts
 
G

Gary Chefetz

Poni:

In the example you use, the value at the task level (what you might be
looking at in project) can be very different from the value at the
assignment level, (what you see in My Tasks in PWA), especially if more than
one resource has assignments on the task. Be sure that you're comparing the
same % complete value fields as well.
 
P

Poni

Hello Ray,

Thank you for the answer but at the Project view I see 100% and at the My
task view I see 0%. What am I missing ?

Thanks

P.
 