Different Values for Actual Work

R

Rayk Grabosch

How can I have different values for actual work on a task ...

1. ...in my project plan
2. ...in the view in my resource's timesheet
3. ...at the summary column of my resource's timesheet when date range is
set to the entire project duration
4. ...in project views?

Thanks for any suggestions!!
 
D

Dale Howard [MVP]

Rayk --

One possible reason is that you have manually entered actuals in the
Microsoft Project plan, but have failed to click Collaborate - Publish -
Republish Assignments, select the "Overwrite actual work entered by
resources", and then click the OK button. Does this explain the source of
the problem? Let us know.
 