i'm using MS Pro 2007, PS 2007, SP1 & Dec Cum.
I have scenario in below:
In MS Pro, for example Task 1 for March 23, in Task Usage:
i enter value for Actual work 12 hrs & actual overtime work 4 hrs, save &
publish it.
Using timephase view, i go to my task, in March 23 coloum for task 1, i can
see 12 hrs with 4 hrs in actual overtime work coloum.
Then i go to my timesheet, in there i see, the values in standard become 12
hrs and in overtime 3 hrs...so total for march 23 is 14 hrs. I believe the
right one is 12 hrs.
Also i tried in MS Project, i enter values for task 2 is 8 hrs in Actual
Overtime Work and in Timesheet will be standard 12 hrs and overtime 12 hrs,
so total for that day become 24 hrs.
anyone know about this problem???
Thanks
I have scenario in below:
In MS Pro, for example Task 1 for March 23, in Task Usage:
i enter value for Actual work 12 hrs & actual overtime work 4 hrs, save &
publish it.
Using timephase view, i go to my task, in March 23 coloum for task 1, i can
see 12 hrs with 4 hrs in actual overtime work coloum.
Then i go to my timesheet, in there i see, the values in standard become 12
hrs and in overtime 3 hrs...so total for march 23 is 14 hrs. I believe the
right one is 12 hrs.
Also i tried in MS Project, i enter values for task 2 is 8 hrs in Actual
Overtime Work and in Timesheet will be standard 12 hrs and overtime 12 hrs,
so total for that day become 24 hrs.
anyone know about this problem???