Just a quick question - can you have different SP levels between client and
server.

ie PS 2007 with SP1 and Project Pro 2007 SP2?
 
R

Rod Gill

Hi,

Not recommended at all. For proper operation most updates require the same
level on client and server.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




MC said:
Just a quick question - can you have different SP levels between client
and
server.

ie PS 2007 with SP1 and Project Pro 2007 SP2?

__________ Information from ESET Smart Security, version of virus
signature database 4465 (20090928) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4465 (20090928) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
M

MC

what are some of the issues?

Rod Gill said:
Hi,

Not recommended at all. For proper operation most updates require the same
level on client and server.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com






__________ Information from ESET Smart Security, version of virus signature database 4465 (20090928) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
M

Mark Everett | PMP

what are some of the issues?











- Show quoted text -

Corruption of the Enterprise Custom Lookup table data values is a key
one. In other words, a Project Manager using Microsoft Project that
is not patched to th same version as Project Server may experience a
situation where the custom lookup table data is different from what is
expected.

Rod is correct that they should be the same version and since the
updates are free, there shouldn't be a reason to not do it.

Hope this helps,
Mark Everett PMP | MCITP
www.catapultsystems.com
 
R

Rod Gill

Worst issue is communication between Project and project server stops
working! If MS has to change how information is sent and the other end
doesn't expect a change, data corruption.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




Mark Everett | PMP said:
Corruption of the Enterprise Custom Lookup table data values is a key
one. In other words, a Project Manager using Microsoft Project that
is not patched to th same version as Project Server may experience a
situation where the custom lookup table data is different from what is
expected.

Rod is correct that they should be the same version and since the
updates are free, there shouldn't be a reason to not do it.

Hope this helps,
Mark Everett PMP | MCITP
www.catapultsystems.com

__________ Information from ESET Smart Security, version of virus
signature database 4468 (20090929) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4468 (20090929) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top