differential sync to actual

  • Thread starter Project Planner - University
  • Start date
P

Project Planner - University

Is it possible to have REAL resources in MSProject 2003 SP3 synced to actual
and the GENERIC resources NOT sync to actual after having set %-complete on
tasks with Generic-ONLY sources.

In other words ... we'd like to track technical progress on tasks that only
have GENERIC resources assigned ... thus, if we set a %-complete, it will
estimate the remaining work on that task for that generic resource.

If I do this now, it resets that task back to 0% as the GENERICS don't
report time via PWA.
 
M

Mike Glen

Hi ,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://project.mvps.org/faqs.htm

Mike Glen
Project MVP



"Project Planner - University"
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top